A device already carries a CE mark. The post-market clinical follow-up study your team is scoping is, on paper, just evidence generation — confirming what the technical documentation already claims. That framing is exactly where Article 74 of the EU Medical Device Regulation catches teams out. The moment a PMCF protocol asks a subject to do something beyond the device's normal conditions of use — an extra visit, an extra blood draw, an extra imaging session — and that something is invasive or burdensome, the study stops being routine surveillance. It becomes a clinical investigation with its own notification clock and its own substantive requirements.
The three-way split PMCF protocols actually fall into
Manufacturers tend to treat PMCF as a single activity with a single governance answer. The regulation splits it three ways, and the split turns entirely on what the protocol asks participants to do and whether the device stays inside its approved use.
- Within intended purpose, no added invasive or burdensome procedures. Registry analysis, questionnaires, review of data already generated in routine care. Outside Article 74(1) entirely — though national law can still impose its own requirements.
- Within intended purpose, added procedures that are invasive or burdensome. Article 74(1) applies: a 30-day notification through the electronic system referenced in Article 73, with Annex XV Chapter II documentation, plus the imported substantive requirements below.
- Outside the device's intended purpose. Article 74(1)'s notification route does not apply at all. Article 74(2) routes the study through the full Articles 62–81 clinical-investigation regime — the same process, and the same timeline, as a device under investigation for the first time.
The protocol decides the regulatory pathway before the first subject is enrolled. Teams that scope the added procedures after the budget and timeline are set are the ones who discover the 30-day clock too late. Why the classification step comes first
What the notification route still requires
It is tempting to read "notification" as lighter than "application" and assume the substantive bar drops with it. It does not. Article 74(1) carries over points (b) through (k) and (m) of Article 62(4) — the core of what a sponsor must demonstrate for any clinical investigation — along with Articles 75 to 77, which govern how competent authorities assess and act on the submission, and Article 80(5) and (6), which layers the investigation's safety reporting into the incident-vigilance framework. A PMCF study that trips Article 74(1) is a notification procedurally and a full clinical investigation substantively. Build the PMCF evaluation report and the underlying protocol with that in mind from the first draft, not after a competent authority asks why the dossier is thin.
Where this sits next to Article 70
Article 74 is the post-market counterpart to the pre-market route most teams already know: a brand-new clinical investigation application under Article 70, assessed before enrollment can begin at all. Article 74(1) exists precisely because a PMCF study on an already-approved device does not need that full pre-assessment cycle to be safe — but "lighter procedure" was never the same claim as "lighter requirements." Scoping the protocol against the intended purpose and the invasive-or-burdensome test, before the study is budgeted, is what keeps a post-market surveillance program from colliding with a clinical-investigation clock nobody planned for.
- Map every added procedure against normal use. List anything the protocol asks of a participant that routine care does not — extra visits, extra sampling, extra imaging.
- Apply the invasive-or-burdensome test. If nothing on the list clears that bar, document why and proceed outside Article 74(1).
- Confirm intended-purpose alignment. If the study uses the device outside its approved intended purpose, plan for the full Article 62–81 timeline, not a 30-day notification.
- Build the 30-day window and the Annex XV dossier into the critical path. Treat the notification date, not the planned enrollment date, as the deadline that drives the schedule.
None of this is a reason to avoid invasive or burdensome PMCF procedures when the clinical question needs them — some post-market evidence genuinely cannot be collected any other way. It is a reason to make the Article 74 classification a scoping-stage decision rather than a discovery made mid-protocol. A PMCF program built around that discipline treats the notification window as a planning input, not a surprise, and arrives at the competent authority with a dossier that already answers the Article 62(4) questions instead of reconstructing them under deadline pressure.
Frequently asked questions
Does every PMCF study need an MDR clinical-investigation notification?
No. Article 74(1) only applies when a post-market clinical follow-up investigation of a CE-marked device, used within its intended purpose, subjects participants to procedures additional to normal conditions of use that are invasive or burdensome. A PMCF activity that stays within normal use — a registry review, a patient questionnaire, analysis of data already collected in routine care — falls outside Article 74(1) entirely, though national rules can still apply.
How much lead time does an Article 74(1) PMCF investigation need?
At least 30 days. The sponsor must notify the Member States concerned before the investigation starts, through the electronic system referenced in Article 73, and include the documentation required by Chapter II of Annex XV. Build that window into the protocol timeline before you lock an enrollment date.
What if the PMCF study uses the device outside its approved intended purpose?
Article 74(1)'s lighter notification route does not apply. Article 74(2) routes that investigation through the full clinical-investigation regime in Articles 62 to 81 — the same application and assessment process as a device under investigation for the first time, not a notification.
Sources & further reading
- Regulation (EU) 2017/745 (MDR), Article 74 — Clinical investigations regarding devices bearing the CE marking. eur-lex.europa.eu
- BfArM (Germany). Notification of a PMCF investigation — national implementation notes. bfarm.de
This article is provided for general informational purposes and reflects the regulatory landscape as of November 2026. It is not legal or regulatory advice. Article 74's paragraph structure, the specific Article 62(4) points it imports, and each Member State's national implementation should be confirmed against the Official Journal text and the relevant competent authority before you rely on a notification date or document list in a protocol or budget.